    EnBW Baltic 1
04.08.2010

SEA POWER has installed the first 3 turbines at EnBW Baltic 1 Offshore Wind Farm - 1 month before schedule.


 
    Rødsand 2
14.07.2010

SEA POWER has installed the last wind turbine at the Rødsand 2 site.

90 turbines in 126 days from the first loading to the last installation. 1,43 day per turbine, including weather, transport etc.

 
  Greater Gabbard
14.07.2010

SEA JACK has installed 8 wind turbines at the Greater Gabbard project.
 

SEA INSTALLER ordered!
12.07.2010

A2SEA has today signed a contract for the building of SEA INSTALLER.
 

The ship that has been specified by A2SEA and will be built according to our design, based on all the experience we have gained from our work in this industry for 10 years is now a reality. We signed a contract with one of the COSCO owned shipyards in China, with expected delivery Q3 2012.
 



 
  EnBW Baltic 1
04.07.2010

SEA WORKER has finished the installation of  monopiles and Transitions pieces


 